Posted on: September 18, 2023[ARCHIVED] ASPHALT RESURFACING

Below is Perrin Asphalt’s paving schedule for the rest of the Richfield Village streets on their 2023 schedule.
MAPLE, TOWNSEND, BRUSHWOOD, GRANT
|
|
|---|
| SEPTEMBER 19 | MILLING |
| SEPTMEBER 20 | PROOF ROLL |
| SEPTEMBER 21-22 | REPAIRS/CASTING ADJUSTMENTS |
| SEPTEMBER 25-29 | CHIP SEAL AND PAVING |
RT 303, BROADVIEW ROAD
|
|
|---|
| SEPTEMBER 19-22 | EXCAVATION OF APRONS/SIDEWALKS |
| SEPTEMBER 25-26 | MILLING OF ROADWAYS |
| SEPTEMBER 27 | PROOF ROLL OF ROADWAYS |
| SEPTEMBER 28-29 | REPAIRS, CASTINGS, ROAD WIDENING |
| OCTOBER 2-6 | CHIP SEAL AND PAVING OF ROADWAYS |