August 4, 2023 8:00 AM

Brecksville Road Closure

Brecksville Road will be closed for 45 days starting August 8th from Townsend Road to 200 yards north of the I-77 bridge over 21.

All TRUCKS will have to use the 77 to Wheatley corridor.
All AUTOs to use Townsend Rd. To Snowville Rd. to Brecksville Rd. -or- Brush Rd. to Black Rd, to Boston Mills Rd. to Brecksville Rd.

Facebook Twitter Email

Latest Update:

September 15, 2023 4:13 PM

NOTICE: UPDATE TO ROAD CLOSURE- Due to some unknown utilities and underground obstructions being hit while lowering the road that is delaying the full opening.  That being said, we believe we will be to a point where we can accommodate emergency vehicles sometime next week.  We will be in contact when we have a more concrete date/time for re-establishing emergency vehicle access.  Thanks for your patience, we appreciate it.  Timothy Sturges-District 12 Office of Construction, ODOT.