Good evening. Thankfully, beginning January 17, 2023, the Cleveland Water Contractor will start to put temporary paving on Broadview Road, starting at the intersection of Rt. 303 and going south to Grant Street, then paving Grant Street. Due to the quantity of steel plates required, they will be able to pave only 400 feet per day. The paving will be covered by steel plates for 3 days before they tackle the next 400-foot section. This is to allow the concrete in the temporary pavement to cure. The Contractor is still installing water line extensions on Rt. 303 west, so that will be the final section paved.
In addition we will be installing 20 mph temporary work zone speed signs. We hope the Contractor will be done with all temporary paving by February 6, 2023 or sooner. In the meantime, please consider alternate routes through Richfield. If you have questions please email me at mwheeler@richfieldvillageohio.org or call me at 330-659-9201 x222. Thank you for your patience during this Cleveland Water project.
Sincerely, Mayor Michael Wheeler