Posted on: September 18, 2023

ASPHALT RESURFACING

Resurfacing_370x370

Below is Perrin Asphalt’s paving schedule for the rest of the Richfield Village streets on their 2023 schedule. 


MAPLE, TOWNSEND, BRUSHWOOD, GRANT

SEPTEMBER 19MILLING
SEPTMEBER 20PROOF ROLL
SEPTEMBER 21-22REPAIRS/CASTING ADJUSTMENTS
SEPTEMBER 25-29CHIP SEAL AND PAVING


RT 303, BROADVIEW ROAD

SEPTEMBER 19-22EXCAVATION OF APRONS/SIDEWALKS
SEPTEMBER 25-26MILLING OF ROADWAYS
SEPTEMBER 27PROOF ROLL OF ROADWAYS
SEPTEMBER 28-29REPAIRS, CASTINGS, ROAD WIDENING
OCTOBER 2-6CHIP SEAL AND PAVING OF ROADWAYS


Facebook Twitter Email

Other News in Home News

VolunteersNeeded-370x370

VOLUNTEERS NEEDED

Posted on: September 19, 2023
FluShots2023-370x370

FLU SHOTS 2023

Posted on: August 31, 2023
AkronZooTiger-370x370

AKRON ZOO

Posted on: August 31, 2023
SR 303 Closure-370x370

UPDATE-ROUTE 303 ROAD CLOSURE

Posted on: August 14, 2023
Brecksville Rd Closure UDPATE-370x370

UPDATE-BRECKSVILLE ROAD CLOSURE

Posted on: August 4, 2023
Playground-370x370

PLAYGROUND PROJECT

Posted on: September 18, 2023
RecycleBin-370x370

ELECTRONICS RECYCLING

Posted on: September 1, 2023
PDCar-LatTransfers-370x370

APPLY TODAY

Posted on: March 9, 2023
Events-Template370x370

VILLAGE EVENTS

Posted on: April 27, 2023
FlagDropBox

Flag Drop Box

Posted on: August 4, 2023
Chairs

Auction Listings

Posted on: January 9, 2023